Monday, 25 February 2013

Brickwork has started

After waiting 3 weeks for the slab to cure, the brickies commenced work last week.

Bricks delivered:

 
Start of the office, laundry & powder room walls:


 Theatre/Living Room walls:

Garage Parapet Boundary Wall:

Fireplace Niche:


View of the Garage boundary from the neighbours side:


Saturday, 26 January 2013

Officially Slabbed!

So after being told no site works would commence for another week, we were pleasantly surprised to see a heap of activity occur, and on Friday morning we've finished the week with a good-looking ground floor slab. We had a few issues on the Friday in relation to the slab pour, had to stop work to ensure some items our third party inspector had picked up were rectified, but all was sorted, and the slab was poured at 9am. Some pics of the week's activities:

Tuesday: Sand backfilled, levelled and compacted:


Thursday: Plumbers came through, and slab footings prepared




Friday: Slab footings finished and Slab poured.


Impressive angle of the Slab depth:


Monday, 21 January 2013

Retaining Walls Completed

Week ending 18th January has seen the Retaining Walls get completed.

Rear boundary retaining complete:

Front and left boundary wall being constructed:




 Retaining walls completed, ready for the next stage:


Friday, 11 January 2013

Construction is underway - Site works

Exciting to post that Construction has officially begun on Monday 7 Jan! It has been an exciting week, I never knew that porta-loos could be that good-looking! So here is a summary of the week's activity with photos:

Monday - Tuesday
Site cleared of all greenery and Porta-loo and clean sand delivered to the site
 

Wednesday
Site excavated and limestone blocks delivered for retaining.




Thursday - Friday
Limestone retaining walls being constructed







Tuesday, 1 January 2013

Pre-Construction Shot

The builder is officially on-site from tomorrow morning! So today we took down the portion of the neighbours boundary fence that sits within our block footprint, so there are no issues come retaining time.
Here is a pic of the block pre-construction start:

The boundary fence we removed today:


Wednesday, 12 December 2012

Final Plans and into Construction

Happy to finally say we have received Final Plans and will be moving to Construction next week! Given it's christmas, not sure I'll get to see any hot tradies on site, but maybe I'm in for a surprise. Here is a preview of the final working plans:

Saturday, 8 December 2012

We have Power!

Amazingly, WP contractor's have done the job in less than a fortnight! So that's quite exciting as it means we can get to site. We have informed the builder, so they are looking now at starting the site levels prior to christmas, which would be fantastic! But I'm not getting over excited just yet - I'll wait until I see people on site. I never thought I would be so excited to see a little green dome, so here it is:



This is an updated pic of the block (with a bit of greenery) prior to start: