Sunday, 29 September 2013

Not too far from Lock-up now, week ending 29/9/13

We can't be too far from lock-up now, the white set has been completed and the house is actually starting to look more like a home than a construction site. Fingers crossed, the week ahead should see the place officially locked-up.

In the meantime, some pics of my close, but yet so far, home to be:

Kitchen Area:


Family Room. Framing for the Fireplace:

Dining Area:

Stacker doors to the Alfresco:

Kitchen Bulkhead:

Looking to the front door from the family room:

Under stairs storage:

Back wall of Theatre with the framing niches:

Front wall of Theatre:

Linen, Powder & Laundry:

Fish Tank in the entry:

Office:

Fish Tank from the Office:

Entry passage view from the front door:

Stairwell:

Main Bedroom feature wall:

Wardrobe:

Bedroom Ceiling:

Stairwell looking down:


Step lights:


Sunday, 1 September 2013

Week Ending 1/9/13

It kind of feels like not much has moved in the last fortnight, but in short, there has been a heap of plumbing, electrical and smart-wiring passed through from upstairs to downstairs. Also the roofing was basically completed on both the Alfresco and Garage.

Electrical and smart-wiring heaven:


Framing for Theatre Room Doors:


 Framing for Gas Fireplace:


Alfresco Roof Framing:


Alfresco Roof Tiling:


Sunday, 11 August 2013

Upstairs structurally completed

Upstairs is structurally completed now, with the windows and doors now installed and the scaffolding taken down. Few other bits I can see done are:
- ceiling and cornices have been installed upstairs
- downpipes, eaves painted and the texture colour applied to the second storey 
- the air-con guys also came back through and have completed the ducting through to downstairs.

View of the house without scaffolding:


Eaves and downpipes:


Balcony Door from inside:


Main bedroom coffit ceiling:



Pic of the cornices:


 View of the texture colour from the back of the house:



And just my luck, that there seems to be quite a magazine collection in my back alfresco. Someone is clearly enjoying the place before I get too!



Saturday, 20 July 2013

Upstairs plaster complete

The last fortnight saw the plaster work upstairs get done.

Main bedroom:

Walk in Robe behind the Bedhead wall:


Ensuite:


 Ensuite shower:

Ensuite toilet:


Kid's Playroom:


Bedroom 2:



Bedroom 3:



Bedroom Four:


Kid's Toilet:

Kid's Bathroom:


Upstairs Linen/storage:

Kid's corridor:


View of the house from the back:



View of the house from the front: