Saturday, 16 March 2013

Brickwork Completed - WE 17 March

There was no update for a fortnight as I was eagerly awaiting the ground floor brickwork finishing! Now that it's all done, here is a sneak preview of our ground floor plan:
 
Garage: 

Front Entry:


Fish Tank Feature Wall, and Study:

Inside Study:
Theatre Room:

Wall Niches in Theatre:
Under stair storage room:
Living room with fireplace:

Alfresco:
Dining:

Kitchen area:
Pantry area:
Entry way passage:


Laundry:
Linen closet:

Powder Room:

View of into house from the backyard:

Half a meterbox:
Little guy enjoying himself on-site:



Sunday, 3 March 2013

Week ending 3/3/13

Fish tank opening in the Entry:


Living room with the fireplace niche:



Powder Room:

Laundry:


Linen Closet:



Dining Room:

 View of our Alfresco from the rear block:


Monday, 25 February 2013

Brickwork has started

After waiting 3 weeks for the slab to cure, the brickies commenced work last week.

Bricks delivered:

 
Start of the office, laundry & powder room walls:


 Theatre/Living Room walls:

Garage Parapet Boundary Wall:

Fireplace Niche:


View of the Garage boundary from the neighbours side:


Saturday, 26 January 2013

Officially Slabbed!

So after being told no site works would commence for another week, we were pleasantly surprised to see a heap of activity occur, and on Friday morning we've finished the week with a good-looking ground floor slab. We had a few issues on the Friday in relation to the slab pour, had to stop work to ensure some items our third party inspector had picked up were rectified, but all was sorted, and the slab was poured at 9am. Some pics of the week's activities:

Tuesday: Sand backfilled, levelled and compacted:


Thursday: Plumbers came through, and slab footings prepared




Friday: Slab footings finished and Slab poured.


Impressive angle of the Slab depth:


Monday, 21 January 2013

Retaining Walls Completed

Week ending 18th January has seen the Retaining Walls get completed.

Rear boundary retaining complete:

Front and left boundary wall being constructed:




 Retaining walls completed, ready for the next stage:


Friday, 11 January 2013

Construction is underway - Site works

Exciting to post that Construction has officially begun on Monday 7 Jan! It has been an exciting week, I never knew that porta-loos could be that good-looking! So here is a summary of the week's activity with photos:

Monday - Tuesday
Site cleared of all greenery and Porta-loo and clean sand delivered to the site
 

Wednesday
Site excavated and limestone blocks delivered for retaining.




Thursday - Friday
Limestone retaining walls being constructed